Work Profile Report [43W592]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0 सं0 3185/111(2)/16-12(एमएलए)/2015 दि0 21.12.2016
TS Amount (lakhs) : 682.64 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
747.22
Resanction Cost :
747.22
Tentative Cost :
738.00
Saving
9.22
Exp. Upto Last Fy :
727.27
For CFY 2024-2025
Remaining :
19.95
Demand :
10.00
Allotment :
9.45
Exp in CFY :
9.45
Total Up to Date Exp :
736.72
Work completed
Sanction on : 8 years 3 days ago
21 Dec 2016
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 1 year 1 month ago
30 Oct 2023
Actual Completion Date : 1 year 2 months ago
30 Sep 2023
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 06-Dec-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: