Work Profile Report [43W695]
Fin Plan
Remarks
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : fजलाfधकारी fअ0 ग0 के पत्र सं0 46/8-fज0यो0-09/2018-19 fद0 11.09.2018
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
53.04
Resanction Cost :
53.04
Tentative Cost :
53.04
Exp. Upto Last Fy :
52.89
For CFY 2024-2025
Remaining :
0.15
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
52.89
Work completed
Sanction on : 6 years 3 months ago
11 Sep 2018
Physical Progress:
At start of FY 2024-2025 :
90 %
Up to Date :
0 %
Tentative Completion date on : 5 years 8 months ago
30 Mar 2019
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण दायित्व शेष। -- as on 31-Jul-2020
Assets :
© PWD Uttarakhand