Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5.3 | 5.3 | 3.650 | 1.65 | 1.000 | 0.000 |
43W724 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0 सं0 1328/111(2)/19-09(एम0एल0ए0) /2015 टी0सी0 दि0 10.03.2019
TS Amount (lakhs) : 261.08 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
291.66
Resanction Cost :
291.66
Tentative Cost :
291.66
Exp. Upto Last Fy : 223.95
For CFY 2024-2025
Remaining : 67.71
Demand : 30.00
Allotment : 5.00
Exp in CFY : 0.00
Total Up to Date Exp : 223.95
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 69 %
Sanction on :
5 years 4 months ago
10 Mar 2019
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पहाड कटान कार्य प्रगति पर । पार्ट द्वितीय प्रगति पर । विवाद के कारण पहाड कटान का कार्य बाधित।विवाद सुलझाने हेतु दि0 20.9.22 को अध्ाि0 अभि0 एवं सहा0 अभि0 द्वारा ग्रामीणों के साथ ख्ुाुली बैठक की गयी परन्तु विवाद सुलझ नही पाया है ।वर्तमान में विवाद सुलझा लिया गया है अनुवन्ध गठित। -- as on 11-Jul-2024
Physical Peramenters