Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.5 | 2.5 | 2.000 | 0.5 | 0.500 | 0.500 |
43W728 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0 सं0 1327/111(2)/19-13(एम0एल0ए0)/ 2017 टी0सी0 दि0 10.03.2019
TS Amount (lakhs) : 158.39 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
158.39
Resanction Cost :
158.39
Tentative Cost :
158.39
Exp. Upto Last Fy : 67.30
For CFY 2024-2025
Remaining : 91.09
Demand : 30.00
Allotment : 0.00
Exp in CFY : 29.20
Total Up to Date Exp : 96.50
Work completed
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 100 %
Sanction on :
5 years 4 months ago
10 Mar 2019
Tentative Completion date:
1 month 2 weeks ago
30 May 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पहाड कटान एवं पार्ट द्वितीय कार्य पूर्ण । -- as on 12-Jul-2024
Physical Peramenters