Work Profile Report [43W753]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0 सं0 3143/111(2)/19-12(एम0एम0ए0)/ 2017 टी0सी0 दि0 08.08.2019
TS Amount (lakhs) : 567.5 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
567.50
Resanction Cost :
608.25
Tentative Cost :
608.25
Exp. Upto Last Fy :
605.18
For CFY 2024-2025
Remaining :
3.07
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
605.18
Work completed
Sanction on : 5 years 4 months ago
08 Aug 2019
Physical Progress:
At start of FY 2024-2025 :
45 %
Up to Date :
100 %
Tentative Completion date on : 10 months 3 weeks ago
31 Jan 2024
Actual Completion Date : 1 year 3 months ago
12 Sep 2023
Physical Linear Components
Remark
कार्य पूर्ण । -- as on 30-Apr-2024