Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3.57 | 0.000 | 3.57 | 0.000 | 0.000 |
43W754 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0 सं0 3191/111(2)/19-13 (प्रा0आ0)/2018 दि0 21.08.2019
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
47.55
Resanction Cost :
47.55
Tentative Cost :
47.55
Exp. Upto Last Fy : 0.56
For CFY 2024-2025
Remaining : 46.99
Demand : 15.00
Allotment : 0.00
Exp in CFY : 2.30
Total Up to Date Exp : 2.86
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
4 years 10 months ago
21 Aug 2019
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
प्रतिकर वितरण प्रगति पर । -- as on 15-Jul-2024