Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.87 | 1.87 | 1.500 | 0.37 | 0.370 | 0.370 |
43W804 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0 सं0 1703/111(2)20-13(एमएलए)/2017 टी0सी0 111 दि0 13.10.2020
TS Amount (lakhs) : 104.19 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
104.19
Resanction Cost :
104.19
Tentative Cost :
104.19
Exp. Upto Last Fy : 84.25
For CFY 2024-2025
Remaining : 19.94
Demand : 19.00
Allotment : 0.00
Exp in CFY : 4.92
Total Up to Date Exp : 89.16
Work completed
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 100 %
Sanction on :
3 years 9 months ago
13 Oct 2020
Tentative Completion date:
1 month 2 weeks ago
30 May 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पहाड कटान एवम् पार्ट द्वितीय का कार्य पूर्ण, दायित्व शेष। -- as on 19-Jun-2024
Physical Peramenters