Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.75 | 2.75 | 2.700 | 0.05 | 0.050 | 0.000 |
43W908 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0 सं0 3234/111(2)/21-13(एमएलए)/2017 टी0सी0-1 दि0 31.08.2021
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
76.10
Resanction Cost :
76.10
Tentative Cost :
76.10
Exp. Upto Last Fy : 40.97
For CFY 2024-2025
Remaining : 35.13
Demand : 35.00
Allotment : 0.00
Exp in CFY : 7.00
Total Up to Date Exp : 47.97
Construction Started
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 98 %
Sanction on :
2 years 10 months ago
31 Aug 2021
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
किमी0 3 में 50 मी0 भाग पर विवाद होने के कारण कार्य अवरूद्ध है। -- as on 09-May-2024
Physical Peramenters