Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.2 | 3.2 | 3.200 | 0 | 0.000 | 0.000 |
43W915 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0 सं0 2612/111(2)21-12/एमएलए/ 2017/टी0सी0-4 दि0 10.08.2021
TS Amount (lakhs) : 74.75 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
74.75
Resanction Cost :
74.75
Tentative Cost :
74.75
Exp. Upto Last Fy : 60.10
For CFY 2024-2025
Remaining : 14.65
Demand : 14.65
Allotment : 0.00
Exp in CFY : 5.60
Total Up to Date Exp : 65.70
Work completed
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 100 %
Sanction on :
2 years 11 months ago
10 Aug 2021
Tentative Completion date:
6 months 2 weeks ago
31 Dec 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण दायित्व शेष। -- as on 12-Jul-2024
Physical Peramenters