Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.75 | 0.75 | 0.750 | 0 | 0.000 | 0.000 |
43W935 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0 सं0 3234/111(2)/21-13(एमएलए)/2017 टी0सी0-1 दि0 31.08.2021
TS Amount (lakhs) : 34.32 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
34.32
Resanction Cost :
34.32
Tentative Cost :
34.32
Exp. Upto Last Fy : 30.75
For CFY 2024-2025
Remaining : 3.57
Demand : 3.57
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 30.75
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 10 months ago
31 Aug 2021
Tentative Completion date:
1 year 4 months ago
24 Feb 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण । -- as on 12-Feb-2024
Physical Peramenters