Work Profile

43W960 :

No Pic Avilable Time series Gantt
मा0 मुख्यमंत्री घोषणा सं0 295/2021 के अन्तर्गत जनपद टिहरी गढ़वाल के विधानसभा क्षेत्र प्रतापनगर में ढुंग-पुजारगांव मो0 मार्ग (एस0सी0एस0पी0) नव निर्माण कार्य द्वितीय चरण स्टेज-1


Work not linked with IM

Bridges on The Basis of AI:

Administrative Approval Detail : e file 36639 dt 31-03-2023

TS Amount (lakhs) : 65.8 Lacs

Financial Detail (in Rs Lakhs)

Sanction Cost :

65.80

Resanction Cost :

65.80

Tentative Cost :

65.80

Exp. Upto Last Fy : 39.90

For CFY 2024-2025

Remaining : 25.90

Demand : 10.00

Allotment : 0.00

Exp in CFY : 0.00

Total Up to Date Exp : 39.90

Construction Started

Physical Progress:

At start of FY 2024-2025 : 0 %

Up to Date : 95 %

Sanction on :
1 year 3 months ago
31 Mar 2023


Tentative Completion date:
2 weeks 3 days ago
30 Jun 2024


Actual Completion Date:
Not Yet Reported


Rating : 95

Remark

Bottelneck: no issue


कार्य प्रगति पर । -- as on 18-Oct-2023

Physical Peramenters

Particulars Sanction Resanction Upto Last Fy For Cfy 2024-2025
Remaining Target Achievement
Length of Road [Km] 2 2 1.900 0.1 0.100 0.000
Currently only Bank Gaurantee information is avilable