Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.25 | 3.25 | 3.000 | 0.25 | 0.250 | 0.250 |
43W976 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0 सं0 1488/111/2/20-13 /एम0एल0ए0/ 2017 TC दि0 14/08/2020
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
243.53
Resanction Cost :
243.53
Tentative Cost :
243.53
Exp. Upto Last Fy : 122.10
For CFY 2024-2025
Remaining : 121.43
Demand : 100.00
Allotment : 100.00
Exp in CFY : 4.48
Total Up to Date Exp : 126.58
Construction Started
Physical Progress:
At start of FY 2024-2025 : 62 %
Up to Date : 90 %
Sanction on :
3 years 7 months ago
18 Nov 2020
Tentative Completion date:
4 months 1 week from now
25 Nov 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पहाड कटान पूर्ण । 15 मी0 स्पान पुल का कार्य प्रगति पर । -- as on 15-Jul-2024