Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.32 | 2.32 | 2.320 | 0 | 0.000 | 0.000 |
43W978 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0 सं0 3984(1)/2/21-12-mla/2017 tc दि0 17.09.2021
TS Amount (lakhs) : 76.91 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
76.91
Resanction Cost :
76.91
Tentative Cost :
76.91
Exp. Upto Last Fy : 59.11
For CFY 2024-2025
Remaining : 17.80
Demand : 17.80
Allotment : 0.00
Exp in CFY : 6.23
Total Up to Date Exp : 65.34
Work completed
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 100 %
Sanction on :
2 years 10 months ago
17 Sep 2021
Tentative Completion date:
1 year 3 months ago
31 Mar 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण । -- as on 02-May-2024
Physical Peramenters