Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5.8 | 5.8 | 5.800 | 0 | 0.000 | 0.000 |
43W981 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : प्रमुख अभि0 का पत्रांक 895/07याता- पी0एम0जी0एस0वाई0-नि0/3 दि0 16.05.2023
TS Amount (lakhs) : 194.16 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
194.16
Resanction Cost :
194.16
Tentative Cost :
194.16
Exp. Upto Last Fy : 159.10
For CFY 2024-2025
Remaining : 35.06
Demand : 35.07
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 159.10
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
1 year 2 months ago
16 May 2023
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण -- as on 25-Apr-2024
Physical Peramenters