Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4.5 | 4.5 | 2.500 | 2 | 2.000 | 2.000 |
43W983 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : प्रमुख अभि0 का पत्रांक 895/07याता- पी0एम0जी0एस0वाई0-नि0/3 दि0 16.05.2023
TS Amount (lakhs) : 87.39 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
87.39
Resanction Cost :
87.39
Tentative Cost :
87.39
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 87.39
Demand : 87.39
Allotment : 0.00
Exp in CFY : 11.38
Total Up to Date Exp : 11.38
Work completed
Physical Progress:
At start of FY 2024-2025 : 60 %
Up to Date : 100 %
Sanction on :
1 year 2 months ago
16 May 2023
Tentative Completion date:
1 month 2 days ago
15 Jun 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
4.50 km में पी सी कार्य पूर्ण। -- as on 15-Jun-2024
Physical Peramenters