Length of Road [Km] | 4.7 | 4.7 | 4.700 | 0 | 0.000 | 0.000 |
43W985 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : e file no 51399 dt 14-07-2023
TS Amount (lakhs) : 136.58 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
136.58
Resanction Cost :
136.58
Tentative Cost :
136.58
Exp. Upto Last Fy : 102.22
For CFY 2024-2025
Remaining : 34.36
Demand : 25.00
Allotment : 0.00
Exp in CFY : 0.42
Total Up to Date Exp : 102.64
Work completed
Physical Progress:
At start of FY 2024-2025 : 45 %
Up to Date : 100 %
Sanction on :
1 year 3 days ago
14 Jul 2023
Tentative Completion date:
2 weeks 3 days ago
30 Jun 2024
Actual Completion Date:
3 months 3 weeks ago
20 Mar 2024
Remark
Bottelneck: no issue
कार्य पूर्ण, दायित्व शेष। -- as on 10-May-2024