Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 128.75 | 128.75 | 103.000 | 25.75 | 25.750 | 0.000 |
43W989 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : प्रमुख अभि0 का प0 सं0 1987/54 बजट (मार्ग/सेतुअनुरक्षण-सड़क सुरक्षा)/2023-24 दि0 10.08.2023
TS Amount (lakhs) : 1171.39 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
1171.39
Resanction Cost :
1171.39
Tentative Cost :
1171.39
Exp. Upto Last Fy : 305.82
For CFY 2024-2025
Remaining : 865.57
Demand : 865.57
Allotment : 0.00
Exp in CFY : 463.35
Total Up to Date Exp : 769.17
Construction Started
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 80 %
Sanction on :
11 months 1 week ago
10 Aug 2023
Tentative Completion date:
1 month 2 weeks from now
01 Sep 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 16-Feb-2024
Physical Peramenters