Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 74.85 | 74.85 | 74.850 | 0 | 0.000 | 0.000 |
43W990 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : प्रमुख अभि0 का प0 सं0 1987/54 बजट (मार्ग/सेतुअनुरक्षण-सड़क सुरक्षा)/2023-24 दि0 10.08.2023
TS Amount (lakhs) : 279.41 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
279.41
Resanction Cost :
279.41
Tentative Cost :
279.41
Exp. Upto Last Fy : 228.58
For CFY 2024-2025
Remaining : 50.83
Demand : 50.83
Allotment : 0.00
Exp in CFY : 12.38
Total Up to Date Exp : 240.96
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
11 months 1 week ago
10 Aug 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 05-Apr-2024
Physical Peramenters