Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 0 | 0 | 0 |
Closed Work 44W219 :
Administrative Approval Detail : शा0सं0 5530/111(2)/10-19(प्रा0आ0)/2010 दिनांक 20-10-2010
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
25.20
Resanction Cost :
25.20
Tentative Cost :
25.20
Exp. Upto Last Fy : 25.19
For CFY 2024-2025
Remaining : 0.01
Demand : 0.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 25.19
Work completed
Physical Progress:
At start of FY 2024-2025 : 69 %
Up to Date : 0 %
Sanction on :
13 years 8 months ago
20 Oct 2010
Tentative Completion date:
3 years 3 months ago
31 Mar 2021
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 31-Mar-2021
Physical Peramenters