Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 10 | 10 | 10 | 0 |
44W450 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या शासनादेश सख्ंया 330/।।।(2) /15-24 (प्रा0आ0)/2014 दिनंाक 14, जनवरी 2015
TS Amount (lakhs) : 442.92 Lacs
Financial Detail
Sanction Cost : 442.92 Lacs
Resanction Cost : 442.92 Lacs
Exp. Upto Last Fy : 108.85 Lacs
For CFY 2024-2025
Remaining : 334.07 Lacs
Demand : 5.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 108.85 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
9 years 4 months ago
14 Jan 2015
Tentative Completion date:
2 years 1 month ago
31 Mar 2022
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। प्रथम 2.00 कि0मी0 लम्बाई में पहाड कटान के उपरान्त ग्राम डोबरी के ग्रामीणों द्वारा विवाद, कार्य बाधित। -- as on 31-Jul-2020
Physical Peramenters