Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 0 | 0 | 0 |
44W562 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या-3548/।।।(2)/18-11 (एम0एल0ए0)/2017 दिनंाक 24 जुलाई, 2018
TS Amount (lakhs) : 27.88 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
43.12
Resanction Cost :
43.12
Tentative Cost :
43.12
Exp. Upto Last Fy : 12.06
For CFY 2024-2025
Remaining : 31.06
Demand : 1.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 12.06
Unstarted Work
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
5 years 11 months ago
24 Jul 2018
Tentative Completion date:
2 years 3 months ago
31 Mar 2022
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
समरेखण स्वीकृत दिनंाक 30.06.2024 तक वनभूमि हस्तान्तरण प्रस्ताव किया जाना प्रस्तावित है। -- as on 14-Jun-2024
Physical Peramenters