Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4.9 | 4.9 | 4.900 | 0 | 0.000 | 0.000 |
44W610 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 2372/(1)/।।।(2)/21-4(प्रा0आ0)/2019 दिनांक 04 अगस्त, 2021
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
360.33
Resanction Cost :
360.33
Tentative Cost :
360.33
Exp. Upto Last Fy : 304.06
For CFY 2024-2025
Remaining : 56.27
Demand : 40.00
Allotment : 0.00
Exp in CFY : 4.76
Total Up to Date Exp : 308.82
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 11 months ago
04 Aug 2021
Tentative Completion date:
1 year 1 month ago
19 May 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व शेष। -- as on 05-Nov-2023
Physical Peramenters