Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5.2 | 5.2 | 1.600 | 3.6 | 0.000 | 0.000 |
44W616 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या- 3586(1)/।।।(2)/21-04 (प्रा0आ0)/2019 दिनंाक 12 सितम्बर, 2021
TS Amount (lakhs) : 352.18 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
352.18
Resanction Cost :
352.18
Tentative Cost :
352.18
Exp. Upto Last Fy : 259.97
For CFY 2024-2025
Remaining : 92.21
Demand : 80.00
Allotment : 13.43
Exp in CFY : 4.58
Total Up to Date Exp : 264.55
Work completed
Physical Progress:
At start of FY 2024-2025 : 58 %
Up to Date : 100 %
Sanction on :
2 years 10 months ago
10 Sep 2021
Tentative Completion date:
1 month 2 weeks ago
31 May 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व शेष। -- as on 16-May-2024
Physical Peramenters