Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.7 | 1.7 | 1.7 | 0 |
44W617 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या-2618(1)/।।।(2)/21-11 (एम0एल0ए0)/2017 टी.सी.।।। दिनंाक 10 अगस्त 2021
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
60.55
Resanction Cost :
60.55
Tentative Cost :
60.55
Exp. Upto Last Fy : 44.65
For CFY 2024-2025
Remaining : 15.90
Demand : 12.75
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 44.65
none
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
2 years 11 months ago
10 Aug 2021
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पार्ट २ का कार्य पूर्ण -- as on 19-Aug-2023
Physical Peramenters