Work Profile Report [44W619]
Tenders
Aggrements
Project Activities
alerts
Samples
Administrative Approval Detail : शासनादेश संख्या 459/।।।(2)/22-06 (एम0एल0ए0)/2017 टीसी दिंनाक 07 जनवरी, 2022
TS Amount (lakhs) : 153.85 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
153.85
Resanction Cost :
153.85
Tentative Cost :
153.85
Exp. Upto Last Fy :
152.85
For CFY 2024-2025
Remaining :
1.00
Demand :
1.00
Allotment :
1.00
Exp in CFY :
1.00
Total Up to Date Exp :
153.85
Work completed
Sanction on : 2 years 11 months ago
07 Jan 2022
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
0 %
Tentative Completion date on : 1 year 5 months ago
30 Jun 2023
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 02-Nov-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: