Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.45 | 2.45 | 2.45 | 0 |
44W626 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या-3257(1)/।।।(2)/21-11 (एम0एल0ए0)/2017 दिनंाक 02 सितम्बर, 2021
TS Amount (lakhs) : 87.38 Lacs
Financial Detail
Sanction Cost : 87.38 Lacs
Resanction Cost : 87.38 Lacs
Exp. Upto Last Fy : 71.40 Lacs
For CFY 2024-2025
Remaining : 15.98 Lacs
Demand : 6.91 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 71.40 Lacs
none
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
1 year 8 months ago
02 Sep 2022
Tentative Completion date:
2 years 1 month ago
31 Mar 2022
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पहाड कटान का कार्य पूर्ण -- as on 15-Dec-2022
Physical Peramenters