Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 4.100 | 0.9 | 0.900 | 0.000 |
44W628 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या-पत्रावली संख्या-22182 लोक निर्माण विभाग अनुभाग-2 देहरादून दिनंाक 29 अगस्त, 2022
TS Amount (lakhs) : 432.12 Lacs
Financial Detail
Sanction Cost : 432.12 Lacs
Resanction Cost : 432.12 Lacs
Exp. Upto Last Fy : 355.23 Lacs
For CFY 2024-2025
Remaining : 76.89 Lacs
Demand : 59.36 Lacs
Allotment : 50.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 355.23 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
1 year 8 months ago
29 Aug 2022
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर -- as on 24-Jun-2023
Physical Peramenters