Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.3 | 1.3 | 1.3 | 0 |
44W629 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई पत्रावली संख्या-22183 लेाक निमार्ण अनुभाग-2 देहरादून, दिनंाक 22 नवम्बर, 2022
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 99.43 Lacs
Resanction Cost : 99.43 Lacs
Exp. Upto Last Fy : 62.79 Lacs
For CFY 2024-2025
Remaining : 36.64 Lacs
Demand : 1.07 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 62.79 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
1 year 5 months ago
22 Nov 2022
Tentative Completion date:
7 months 2 weeks ago
30 Sep 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व शेष। -- as on 03-Oct-2023
Physical Peramenters