Work Profile Report : 44W630
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : शासनादेश संख्या-4990(1)/।।।(2)/21-39 (प्रा0आ0)/2018 दिनंाक 22 अक्टूबर, 2021
TS Amount (lakhs) : 489.89 Lacs
Budget Financial Head : Building ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
489.89
Resanction Cost :
489.89
Tentative Cost :
489.89
Exp. Upto Last Fy :
291.05
For CFY 2025-2026
Remaining :
198.84
Demand :
120.00
Allotment :
120.00
Exp in CFY :
6.62
Total Up to Date Exp :
297.67
Construction Started
Sanction on : 4 years 3 months ago
22 Oct 2021
Physical Progress:
At start of FY 2025-2026 :
65 %
Up to Date :
74 %
Tentative Completion date on : 1 month 2 weeks from now
30 Mar 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Inner and outer plaster work complete.
floor tile work complete.
Whitewash work and putty work under progress.
Sanitary work under progress
-- as on 07-Feb-2026
Assets :
Work not linked with IM
Bridges on The Basis of AI: