Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4.25 | 4.25 | 4.250 | 0 | 0.000 | 0.000 |
44W638 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई पत्रावली संख्या-48762 लोक निर्माण अनुभाग-2 देहरादून दिनंाक 14 फरवरी, 2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
261.07
Resanction Cost :
261.07
Tentative Cost :
261.07
Exp. Upto Last Fy : 180.58
For CFY 2024-2025
Remaining : 80.49
Demand : 40.00
Allotment : 40.00
Exp in CFY : 5.86
Total Up to Date Exp : 186.44
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
1 year 5 months ago
14 Feb 2023
Tentative Completion date:
1 year 2 months ago
13 May 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 06-Jun-2024
Physical Peramenters