Work Profile Report [44W638]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : ई पत्रावली संख्या-48762 लोक निर्माण अनुभाग-2 देहरादून दिनंाक 14 फरवरी, 2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
261.07
Resanction Cost :
261.07
Tentative Cost :
261.07
Exp. Upto Last Fy :
220.17
For CFY 2024-2025
Remaining :
40.90
Demand :
25.29
Allotment :
40.00
Exp in CFY :
23.88
Total Up to Date Exp :
244.05
Work completed
Sanction on : 1 year 10 months ago
14 Feb 2023
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 1 year 7 months ago
13 May 2023
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 06-Jun-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: