Work Profile Report [44W665]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : प्रमुख अभियन्ता (विभागाध्यक्ष) लोक निर्माण विभाग उत्तराखण्ड, देहरादून के पत्रांक 895/07 याता0-पी0एम0जी0एस0वाई0-नि0 ।।। दिनांक 16.05.2023
TS Amount (lakhs) : 69.54 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
69.54
Resanction Cost :
69.54
Tentative Cost :
69.25
Saving
0.29
Exp. Upto Last Fy :
66.10
For CFY 2024-2025
Remaining :
3.44
Demand :
3.44
Allotment :
3.14
Exp in CFY :
3.14
Total Up to Date Exp :
69.24
Work completed
Sanction on : 1 year 7 months ago
16 May 2023
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
100 %
Tentative Completion date on : 7 months 3 weeks ago
29 Apr 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Saving 0.29 has been recorded as expected cost of work reduced from 69.54 to 69.25 . -- as on 10-Dec-2024