Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 7.9 | 7.9 | 0.000 | 7.9 | 0.000 | 0.000 |
44W665 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : प्रमुख अभियन्ता (विभागाध्यक्ष) लोक निर्माण विभाग उत्तराखण्ड, देहरादून के पत्रांक 895/07 याता0-पी0एम0जी0एस0वाई0-नि0 ।।। दिनांक 16.05.2023
TS Amount (lakhs) : 69.54 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
69.54
Resanction Cost :
69.54
Tentative Cost :
69.54
Exp. Upto Last Fy : 48.91
For CFY 2024-2025
Remaining : 20.63
Demand : 3.44
Allotment : 0.00
Exp in CFY : 17.19
Total Up to Date Exp : 66.10
Work completed
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 100 %
Sanction on :
1 year 2 months ago
16 May 2023
Tentative Completion date:
2 months 2 weeks ago
29 Apr 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 06-Jun-2024
Physical Peramenters