Work Profile Report [44W665]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : प्रमुख अभियन्ता (विभागाध्यक्ष) लोक निर्माण विभाग उत्तराखण्ड, देहरादून के पत्रांक 895/07 याता0-पी0एम0जी0एस0वाई0-नि0 ।।। दिनांक 16.05.2023
TS Amount (lakhs) : 69.54 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
69.54
Resanction Cost :
69.54
Tentative Cost :
69.54
Exp. Upto Last Fy :
48.91
For CFY 2024-2025
Remaining :
20.63
Demand :
3.44
Allotment :
0.00
Exp in CFY :
17.19
Total Up to Date Exp :
66.10
Work completed
Sanction on : 1 year 6 months ago
16 May 2023
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
100 %
Tentative Completion date on : 6 months 3 weeks ago
29 Apr 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 06-Jun-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: