Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 14.5 | 14.5 | 14.5 | 0 |
44W666 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : प्रमुख अभियन्ता (विभागाध्यक्ष) लोक निर्माण विभाग उत्तराखण्ड, देहरादून के पत्रांक 895/07 याता0-पी0एम0जी0एस0वाई0-नि0 ।।। दिनांक 16.05.2023
TS Amount (lakhs) : 83.58 Lacs
Financial Detail
Sanction Cost : 83.58 Lacs
Resanction Cost : 83.58 Lacs
Exp. Upto Last Fy : 50.00 Lacs
For CFY 2024-2025
Remaining : 33.58 Lacs
Demand : 33.58 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 50.00 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
1 year 3 days ago
16 May 2023
Tentative Completion date:
1 month 2 weeks ago
03 Apr 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
क्षतिग्रस्त दीवारों का निर्माण कार्य प्रगति पर है। -- as on 14-Dec-2023
Physical Peramenters