Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 18.85 | 18.85 | 18.85 | 0 |
44W668 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासानादेश ई पत्रावली संख्या-48456 लोक निर्माण अनुभाग 2 देहरादून दिनांक 21.08.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 273.03 Lacs
Resanction Cost : 273.03 Lacs
Exp. Upto Last Fy : 0.00 Lacs
For CFY 2024-2025
Remaining : 273.03 Lacs
Demand : 113.01 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 0.00 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
8 months 4 weeks ago
21 Aug 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 03-Feb-2024
Physical Peramenters