Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.84 | 2.84 | 1.500 | 1.34 | 1.340 | 1.340 |
44W669 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासानादेश ई पत्रावली संख्या-48456 लोक निर्माण अनुभाग 2 देहरादून दिनांक 21.08.2023
TS Amount (lakhs) : 72.41 Lacs
Financial Detail
Sanction Cost : 72.41 Lacs
Resanction Cost : 72.41 Lacs
Exp. Upto Last Fy : 31.83 Lacs
For CFY 2024-2025
Remaining : 40.58 Lacs
Demand : 3.64 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 31.83 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 100 %
Sanction on :
8 months 4 weeks ago
21 Aug 2023
Tentative Completion date:
6 days 3 hours ago
13 May 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व शेष। -- as on 14-May-2024
Physical Peramenters