Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.13 | 1.13 | 0.000 | 1.13 | 1.130 | 0.000 |
44W693 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या-ई पत्रावली संख्या-22183 लोक निर्माण अनुभाग-2 दिनांक 12 अक्टूबर, 2023
TS Amount (lakhs) : 81.72 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
81.72
Resanction Cost :
81.72
Tentative Cost :
81.72
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 81.72
Demand : 30.00
Allotment : 30.00
Exp in CFY : 15.29
Total Up to Date Exp : 15.29
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 20 %
Sanction on :
9 months 5 days ago
12 Oct 2023
Tentative Completion date:
3 months 2 weeks from now
01 Nov 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
सोलिंग का कार्य पूर्ण। इन्टर कोट का कार्य प्रगति पर। -- as on 18-Jun-2024