Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 3 | 0 |
44W701 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0- 3930/111(2)/09-08(एम0एल0ए0)/08 टी0सी0 दिनांक 02.03.2009
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 105.00 Lacs
Resanction Cost : 105.00 Lacs
Exp. Upto Last Fy : 60.71 Lacs
For CFY 2024-2025
Remaining : 44.29 Lacs
Demand : 41.43 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 60.71 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
15 years 2 months ago
02 Mar 2009
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 07-Feb-2024