Work Profile Report [44W710]

जनपद टिहरी गढवाल मे आगराखाल कुसरैला मोटर मार्ग पर कुण्ड से कोडारना मोटर मार्ग
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

  • Documents
  • Samples

Administrative Approval Detail : शा0सं0- 3930/111(2)/09-08(एम0एल0ए0)/08 टी0सी0 दिनांक 02.03.2009

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

350.00

Resanction Cost :

350.00

Tentative Cost :

350.00

Exp. Upto Last Fy :

120.72

For CFY 2025-2026

Remaining :

229.28

Demand :

0.00

Allotment :

3.63

Exp in CFY :

3.63

Total Up to Date Exp :

124.36

Work deferred

Sanction on : 16 years 3 months ago

02 Mar 2009

Physical Progress:

At start of FY 2025-2026 :

1 %

Up to Date :

0 %

Tentative Completion date on : 8 months 4 weeks from now

31 Mar 2026

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
10
10
0.000
10
0.000
0.000

Remark

view all

ग्राम सभा दिउली एवं खर्की के ग्रामवासियों के मध्य समरेखण विवाद को सुलझाने का प्रयास किया जा रहा है। -- as on 11-Apr-2025

Rating : 39

No Forest Case in The Work

Hindrance / Bottleneck : Alignment Dispute

Assets :

Work not linked with IM

Bridges on The Basis of AI: