Work Profile Report [44W710]

जनपद टिहरी गढवाल मे आगराखाल कुसरैला मोटर मार्ग पर कुण्ड से कोडारना मोटर मार्ग
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

  • Documents
  • Samples

Administrative Approval Detail : शा0सं0- 3930/111(2)/09-08(एम0एल0ए0)/08 टी0सी0 दिनांक 02.03.2009

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

350.00

Resanction Cost :

350.00

Tentative Cost :

350.00

Exp. Upto Last Fy :

120.72

For CFY 2025-2026

Remaining :

229.28

Demand :

0.00

Allotment :

3.63

Exp in CFY :

3.63

Total Up to Date Exp :

124.36

Work deferred

Sanction on : 16 years 6 months ago

02 Mar 2009

Physical Progress:

At start of FY 2025-2026 :

1 %

Up to Date :

0 %

Tentative Completion date on : 6 months 2 weeks from now

31 Mar 2026

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
10
10
0.000
10
0.000
0.000

Remark

view all

उक्त मोटर मार्ग के समरेखण में ग्राम दिउली एवं खर्की के ग्रामीणों द्वारा भूमि विवाद किया जा रहा है। जिस कारण पहाड कटान का कार्य नही हो सका है। कार्यालय सहायक अभियन्ता के पत्रांक 150/1एम0जी0 दिनंाक 15.06.2025 द्वारा ग्राम प्रधान (प्रशासक) को वार्ता करने हेतु पत्र पे्रषित किया गया था। विभाग द्वारा दिनांक 26-06-2025 को सहायक अभियन्ता तथा अपर सहायक अभियन्ता द्वारा स्थानीय क्षेत्र पंचायत सदस्य एवं ग्रामीणों की उपस्थिति मे स्थलीय निरीक्षण के उपरान्त ग्रामवासियों से वार्ता कर विवाद सुलझाने का प्रयास किया गया। परन्तु आतिथि तक ग्रामवासियों द्वारा सहमति प्रदान नही की गई है। (भूमि विवाद होने के कारण वित्तीय वर्ष 2025-26 में लक्ष्य नही रखा गया है।) -- as on 15-Jul-2025

Rating : 39

No Forest Case in The Work

Hindrance / Bottleneck : Alignment Dispute

Assets :

Work not linked with IM

Bridges on The Basis of AI: