Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 20 | 20 | 0.000 | 20 | 0.000 | 0.000 |
44W711 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 2755/111(2)/06-52 (प्रा0आ0)/06 दिनांक 10.11.2006
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
324.00
Resanction Cost :
324.00
Tentative Cost :
324.00
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 324.00
Demand : 2.00
Allotment : 0.00
Exp in CFY : 3.87
Total Up to Date Exp : 3.87
Unstarted Work
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
17 years 8 months ago
10 Nov 2006
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: Alignment Dispute
भूमि विवाद। -- as on 06-Jun-2024
Physical Peramenters