Work Profile Report : 45W173

घनसाली-कोटी-अखोड़ी मोटर मार्ग के कि0मी0-13 (बांझगला) से अरोली-पंतवालगावं-सिल्ला-जाख तक मोटर मार्ग का निव निर्माण कार्य। (प्रथम चरण)
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

  • Documents
  • Samples

Administrative Approval Detail : 451/।।।(2)/20-09(एम0एल0ए0)/2017 टी0सी0, दिनांक 28.01.2020

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

15.52

Resanction Cost :

15.52

Tentative Cost :

15.52

Exp. Upto Last Fy :

1.01

For CFY 2025-2026

Remaining :

14.51

Demand :

0.50

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

1.01

Alignment Approved

Sanction on : 6 years 2 weeks ago

28 Jan 2020

Physical Progress:

At start of FY 2025-2026 :

5 %

Up to Date :

5 %

Tentative Completion date on : 1 year 1 month from now

31 Mar 2027

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
4
0
0.000
0
0.000
0.000

Remark

view all

कार्यालय प्रभागीय वनाधिकारी, वन प्रभाग नई टिहरी के द्वारा दिनांक-01.12.2025 को वनभूमि पत्रावली आॅनलाईन आपत्तियों में वापस लौटाया गया है, आपत्ति के निराकरण हेतु कार्यालय प्रभागीय वनाधिकारी वन प्रभाग, नई टिहरी के पत्रांक-1390/12-1, दिनांक-31.12.2025 के सन्दर्भ में संयुक्त निरीक्षण किया गया जिसमें वृक्षों की गणना की गयी, जिसकी संयुक्त आख्या अपेक्षित है। -- as on 27-Jan-2026

Rating : 9

Forest Case Pending At : 04: DFO

Hindrance / Bottleneck : Long Term Forest Approval

Assets :

Work not linked with IM

Bridges on The Basis of AI: