Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 0 | 0.000 | 0 | 0.000 | 0.000 |
45W177 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 451/।।।(2)/20-09(एम0एल0ए0)/2017 टी0सी0, दिनांक 28.01.2020
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
21.38
Resanction Cost :
21.38
Tentative Cost :
21.38
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 21.38
Demand : 1.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.00
Unstarted Work
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
4 years 5 months ago
28 Jan 2020
Tentative Completion date:
2 years 3 months ago
31 Mar 2022
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: Alignment Dispute
काश्तकारों द्वारा सर्वेक्षण विवाद किया जा रहा है। -- as on 31-Jul-2020
Physical Peramenters