Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 5.000 | 0 | 0.000 | 0.000 |
45W190 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0-2139(1)/।।।(2)/20-09(एम0एल0ए0)/2017 टी0सी0आई0, दि0 27.11.2020
TS Amount (lakhs) : 286.81 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
286.81
Resanction Cost :
286.81
Tentative Cost :
286.81
Exp. Upto Last Fy : 283.91
For CFY 2024-2025
Remaining : 2.90
Demand : 2.90
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 283.91
In Maintenance After Completion
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
3 years 7 months ago
27 Nov 2020
Tentative Completion date:
1 year 8 months ago
18 Oct 2022
Actual Completion Date:
1 year 8 months ago
18 Oct 2022
Remark
Bottelneck: no issue
कार्य पूर्ण।कार्य तीन वर्षीय अनुरक्षण के अन्तर्गत है। -- as on 02-Oct-2023