Work Profile Report [45W192]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0-2273(1)/।।।(2)/20-9(एम0एल0ए0)2017टी0सी04, दि0 23.12.2020
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
194.30
Resanction Cost :
194.30
Tentative Cost :
194.30
Exp. Upto Last Fy :
194.29
For CFY 2025-2026
Remaining :
0.01
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
194.29
Work completed
Sanction on : 4 years 6 months ago
23 Dec 2020
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 3 months 6 days ago
30 Mar 2025
Actual Completion Date : 2 years 2 months ago
16 Apr 2023
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 08-Sep-2023
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand