Work Profile Report [45W200]

मा0मु0घो0 संख्या-404/2013 के अन्तर्गत जगदीशिला-हिन्दाव मोटर मार्ग का निर्माण कार्यं।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

    alerts

  • Documents
  • Samples

Administrative Approval Detail : 164(1)/।।।(2)/21-09(एम0एल0ए0)/2017, दिनांक-03.02.2021

TS Amount (lakhs) : 280.3 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

280.30

Resanction Cost :

280.30

Tentative Cost :

280.30

Exp. Upto Last Fy :

248.20

For CFY 2024-2025

Remaining :

32.10

Demand :

32.09

Allotment :

32.09

Exp in CFY :

11.85

Total Up to Date Exp :

260.05

Construction Started

Sanction on : 3 years 10 months ago

03 Feb 2021

Physical Progress:

At start of FY 2024-2025 :

100 %

Up to Date :

100 %

Tentative Completion date on : 2 months 3 days from now

28 Feb 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
4
4
4.000
0
0.000
0.000

Remark

view all

पहाड कटान एवं प्रतिधारक दीवारों का निर्माण कार्य पूर्ण। कुछ स्थानों पर ब्रे्स्टवाल एवं क्षतिग्रस्त रास्तों का निर्माण कार्य शेष। -- as on 21-Dec-2024

Rating : 110

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: