Work Profile Report [45W222]
Remarks
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 5299(1)/।।।(2)/21-09(एम0एल0ए0)/2017 TCI, दिनांक-01.11.2021
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
73.55
Resanction Cost :
73.55
Tentative Cost :
73.55
Exp. Upto Last Fy :
65.61
For CFY 2024-2025
Remaining :
7.94
Demand :
7.93
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
65.61
Work completed
Sanction on : 3 years 1 month ago
01 Nov 2021
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 3 months 5 days from now
30 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 08-Sep-2023
Assets :
Work not linked with IM
Bridges on The Basis of AI: