Work Profile Report [45W224]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : 5460/।।।(2)/21-09(एम0एल0ए0)/2017 TCVI, दिनांक-16.11.2021
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
52.58
Resanction Cost :
52.58
Tentative Cost :
52.58
Exp. Upto Last Fy :
52.54
For CFY 2025-2026
Remaining :
0.04
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
52.54
Work completed
Sanction on : 3 years 7 months ago
16 Nov 2021
Physical Progress:
At start of FY 2025-2026 :
83 %
Up to Date :
100 %
Tentative Completion date on : 3 months 3 weeks ago
18 Mar 2025
Actual Completion Date : 3 months 3 weeks ago
18 Mar 2025
Physical Linear Components
Remark
WORK COMPLETED. -- as on 03-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: