Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.9 | 0.9 | 0.900 | 0 | 0.000 | 0.000 |
45W227 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 6036(1)/।।।(2)/21-09(एम0एल0ए0)/2017, दिनांक-15.12.2021
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
48.40
Resanction Cost :
48.40
Tentative Cost :
48.40
Exp. Upto Last Fy : 45.68
For CFY 2024-2025
Remaining : 2.72
Demand : 2.72
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 45.68
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 7 months ago
15 Dec 2021
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 08-Sep-2023
Physical Peramenters