राज्य योजना के अन्तर्गत रीह से लोणी मोटर मार्ग का निर्माण कार्य।


Work not linked with IM

Bridges on The Basis of AI:

Administrative Approval Detail : शासन की ई0 पत्रावली सं0-32588,दि0-14.11.2022

TS Amount (lakhs) : 0 Lacs

Financial Detail (in Rs Lakhs)

Sanction Cost :

7.50

Resanction Cost :

7.50

Tentative Cost :

7.50

Exp. Upto Last Fy : 0.10

For CFY 2024-2025

Remaining : 7.40

Demand : 0.50

Allotment : 0.00

Exp in CFY : 0.00

Total Up to Date Exp : 0.10

Physical Progress:

At start of FY 2024-2025 : 0 %

Up to Date : 0 %

Sanction on :
1 year 8 months ago
14 Nov 2022


Tentative Completion date:
Yet To Decide


Actual Completion Date:
Not Yet Reported


Rating : 1

Remark

Bottelneck:


Physical Peramenters

Particulars Sanction Resanction Upto Last Fy For Cfy 2024-2025
Remaining Target Achievement
Length of Road [Km] 5 5 5.000 0 0.000 0.000