Work Profile Report [45W239]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासन की ई0 पत्रावली सं0-37103,दि0-09.11.2022
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
99.97
Resanction Cost :
99.97
Tentative Cost :
99.97
Exp. Upto Last Fy :
99.97
For CFY 2025-2026
Remaining :
0.00
Demand :
0.00
Allotment :
0.00
Exp in CFY :
1.87
Total Up to Date Exp :
101.84
Work completed
Sanction on : 2 years 7 months ago
09 Nov 2022
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 4 months 3 days ago
28 Feb 2025
Actual Completion Date : 3 months 3 weeks ago
04 Mar 2025
Physical Linear Components
Remark
work completed. -- as on 03-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand