Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.05 | 2.05 | 2.05 | 0 |
45W240 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासन की ई0 पत्रावली सं0-37103,दि0-09.11.2022
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
61.71
Resanction Cost :
61.71
Tentative Cost :
61.71
Exp. Upto Last Fy : 56.92
For CFY 2024-2025
Remaining : 4.79
Demand : 4.79
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 56.92
Construction Started
Physical Progress:
At start of FY 2024-2025 : 98 %
Up to Date : 98 %
Sanction on :
1 year 8 months ago
09 Nov 2022
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पहाड कटान का कार्य प्रगति पर। -- as on 08-Sep-2023