Work Profile

पिलखी-नैल-बौंसला-वनचुरी मोटर मार्ग के किमी. 0.00 से किमी. 4.80 तक मोटर मार्ग में पी.सी. द्वारा डामरीकरण कार्य।


Work not linked with IM

Bridges on The Basis of AI:

Administrative Approval Detail : ई पत्रावली संख्या-32588, दिनांक-06.03.2023

TS Amount (lakhs) : 372.8 Lacs

Financial Detail (in Rs Lakhs)

Sanction Cost :

372.80

Resanction Cost :

372.80

Tentative Cost :

372.80

Exp. Upto Last Fy : 221.55

For CFY 2024-2025

Remaining : 151.25

Demand : 151.25

Allotment : 139.08

Exp in CFY : 114.93

Total Up to Date Exp : 336.48

Construction Started

Physical Progress:

At start of FY 2024-2025 : 60 %

Up to Date : 95 %

Sanction on :
1 year 4 months ago
06 Mar 2023


Tentative Completion date:
1 month 1 week from now
30 Aug 2024


Actual Completion Date:
Not Yet Reported


Rating : 114

Remark

Bottelneck: no issue


G1,G2 and G3 in 4.80 km completed.premix carpet completed in 4.80 km. Patri filling coolie walling and balanced drain, road safety and parapet work in progress. -- as on 13-Jul-2024

Physical Peramenters

Particulars Sanction Resanction Upto Last Fy For Cfy 2024-2025
Remaining Target Achievement
Length of Road [Km] 4.8 4.8 0.000 4.8 4.800 0.000
Currently only Bank Gaurantee information is avilable