Work Profile

पिलखी-नैल-बौंसला-वनचुरी मोटर मार्ग के किमी. 0.00 से किमी. 4.80 तक मोटर मार्ग में पी.सी. द्वारा डामरीकरण कार्य।


Work not linked with IM

Bridges on The Basis of AI:

Administrative Approval Detail : ई पत्रावली संख्या-32588, दिनांक-06.03.2023

TS Amount (lakhs) : 372.8 Lacs

Financial Detail

Sanction Cost : 372.80 Lacs

Resanction Cost : 372.80 Lacs

Exp. Upto Last Fy : 221.55 Lacs

For CFY 2024-2025

Remaining : 151.25 Lacs

Demand : 151.25 Lacs

Allotment : 12.92 Lacs

Exp in CFY : 0.00 Lacs

Total Up to Date Exp : 221.55 Lacs

Construction Started

Physical Progress:

At start of FY 2024-2025 : 60 %

Up to Date : 65 %

Sanction on :
1 year 2 months ago
06 Mar 2023


Tentative Completion date:
3 weeks 3 days from now
13 Jun 2024


Actual Completion Date:
Not Yet Reported


Rating : 74

Remark

Bottelneck: no issue


G1 in 4.80 km, G2 in 4.80 km completed.G3 work in progress. -- as on 10-Apr-2024

Physical Peramenters

Particulars Sanction Resanction Upto Last Fy For Cfy 2024-2025
Remaining Target Achievement
Length of Road [Km] 4.8 4.8 0.000 4.8 4.800 0.000
Currently only Bank Gaurantee information is avilable